Report from the building site Shopping Mall “Grozny Mall”: Overhanging utilities systems and communications from the built-up area of the site

Вынос инженерных сетей с территории застройки объекта ТРЦ "ГРОЗНЫЙ МОЛЛ"

The work on overhanging utilities systems and communications from the built-up area project land Shopping Mall “Grozny Mall” are performed in accordance with predicated schedule. The work on overhanging a water supply system and a storm water sewer from the built-up area project land Shopping Mall “Grozny Mall” is started on September 2016. The new water supply system 400 mm in diameter and the storm water sewer 1000 mm in diameter are routing on the raceway according to the previous prepared detailed documentation as agreed by Grozny city administration. The works are in lock-up stage.

At 15.11.2016:

  • 555 meters non-artesian pipe of the storm water sewer 1000 mm in diameter is routed.
  • 9 sewer manholes and 5 storm water basins are installed.
  • 3 water-line cameras are installed.
  • Shut-off valves and fire hydrant are setting up.
  • 570 m trenches for providing water supply system are prepared and 250 m pipe is routed.

The present city storm drainage system rainfall discharge in Leninsky district Grozny city will be improved after conclusion this works.